2020 CONSTRUCTION PHOTOS
December 2020
- At the future Maintenance and Storage facility, the interior buildout continues with the installation of duct work.
- A crew member prepares for the installation of glazing at the future Maintenance and Storage facility.
- Underground utilities are installed prior to concrete placement where the guideway will transition from elevated to at-grade.
- The construction of columns that will support the future West CTA station parking structure has begun.
- Falsework and formwork is constructed where the APM guideway will curve around the LAX Theme Building in front of the LAX Terminal 2 project.
- Formwork has been constructed where the APM guideway will span the future Metro Crenshaw/LAX Line.
November 2020
- Construction continues on the APM guideway segment that will service the future West CTA station.
- Crews construct the concrete support structure for the future Center CTA station.
-
Ironworkers install reinforcement bar prior to concrete placement.
- Once complete, the APM guideway will pass by the iconic LAX Theme Building.
- Formwork is constructed atop a falsework platform, into which concrete will eventually be placed.
- The interior buildout of the future Maintenance Storage Facility continues with ductwork.
- Concrete pours for the system's only at-grade tracks are now complete; guiding elements to follow.
- Formwork has been stripped revealing the first segment of completed guideway superstructure.
- Machinery to spread concrete is installed on rails prior to the final concrete placement.
- APM guideway construction advances across the 96th Street roadway as it approaches Century Boulevard.
October 2020
- Concrete is placed inside the future Maintenance and Storage facility for the second level floor.
- APM guideway columns are constructed near the future Consolidated Rent-A-Car facility.
- Station construction continues at the future Intermodal Transportation Facility-East.
- The erection of falsework where the APM guideway approaches Airport Blvd precedes the construction of formwork and concrete placement.
- Workers perform maintenance on a crane used to lift construction materials onto the APM guideway falsework.
- Crews construct formwork for guideway concrete placement at the future East Central Terminal Area station.
- LINXS and LAWA personnel survey construction progress at the future East Central Terminal Area station.
- LINXS and LAWA personnel survey construction progress at the future East Central Terminal Area station.
- LINXS and LAWA personnel survey construction progress at the future East Central Terminal Area station.
- LINXS and LAWA personnel survey construction progress at the future East Central Terminal Area station.
- Falsework steel deliniates the path of the APM guideway as it moves through the LAX Central Terminal Area.
- Construction of the future Center Central Terminal Area station continues to advances within view of the iconic LAX Theme Building.
- Workers place concrete for the foundation of the future West Central Terminal Area station.
September 2020
- Workers verify correct placement of the guideway reinforcement bar.
- Preparations for concrete placement continue as the APM guideway approaches Century Boulevard.
- Work continues on the guideway segment that will service the future East CTA station.
- Crews work to install reinforcement bar in guideway formwork in advance of concrete placement.
- Falsework delineates where the guideway will converge west of the future East CTA station.
- At the future West CTA station, tower cranes have been installed to facilitate new stages of construction.
- Column construction has begun for the guideway segment that will service the future Consolidated Rent-A-Car facility.
- Work on bents and upper columns for the future East-ITF station is underway.
- The future East-ITF station will establish a direct connection to regional transportation at the Airport Metro Connector.
August 2020
- At the APM's future Maintenance and Storage Facility, work on the exterior walls and roof have begun.
- Track work continues at the APM's future Maintenance and Storage Facility.
- Workers construct the concrete tracks that will take the APM through the system's train wash facility.
- Station construction continues at the site of the Intermodal Transportation Facility-East.
- At the future Intermodal Tranpsortation Facility-East, crews work to construct the columns that will support the station.
- Workers install a temporary power system for the tower cranes that will construct the future West Central Terminal Area station.
- At the site of the future Center Central Terminal Area station, column work continues.
- The APM will cross 96th street as it leaves LAX and approaches the future Intermodal Transportation Facility-West.
July 2020
- Reinforcement bar is installed inside the guideway forms in preparation for concrete.
- Crews place rebar for concrete structures at future ITF-West station to support the station's platform.
- Falsework will support the construction of the guideway east of the future ITF-West station.
- A worker erects falsework which will support guideway construction.
- Steel erection continues at the APM's future Maintenance and Storage Facility.
- Workers place concrete for track at the future Maintenance and Storage Facility.
- Column construction continues to advance where APM will pass by the LAX Theme Building.
- Once guideway construction is complete at East CTA station, construction can begin.
-
APM construction rises above Upper East Way.
- Column rebar is set in anticipation for guideway construction near West CTA station.
- Crews prepare the reinforcing steel for the foundation grade beams at the future West CTA station.
June 2020
- Utility relocation and foundation work continues at the site of the future Center CTA station.
- Falsework is erected to enable guideway construction at the future East CTA station.
- Concrete for the final two upper columns at the future East CTA station cures.
- Crews install pile caps, prefab metal forms and place grade beam steel at the future West CTA station.
- Skilled craft measures prefabricated metal forms at the future West CTA station.
- Utilizing a cast-in-place technique, guideway formwork is constructed in preparation for concrete placement.
- At the future ITF-West station, dual tracks leading into and out of the station will converge into a single track.
- Falsework and formwork to enable guideway construction is in place for a segment of guideway near the future ITF-West station.
- Falsework materials are staged for guideway construction at future East-ITF station and Airport Metro Connector.
- Once the guideway is complete at the future ITF-West station, station construction can begin.
May 2020
- Crews construct three new guideway columns near the ITF West.
- Falsework spans 96th street to allow for traffic circulation as guideway construction continues.
- Falsework creates a platform to support guideway formwork near 96th Street.
- A crew places concrete into column formwork where the guideway approaches Century Boulevard.
- The system's first sections of track were constructed at the Maintenance and Storage Facility.
- Concrete workers finish a slab at the Maintenance and Storage Facility.
- The Maintenance and Storage Facility takes sshape as structural steel work continues.
- Crews reinforce a bent at the ITF West through a process called post-tensioning.
- Workers install column forms into which concrete will be placed at East Central Terminal Station.
- Work continues on the upper columns that will support the platform level at East Central Terminal Station.
April 2020
- Guideway columns are prepared to be poured
- Future Consolidated Rental Car Facility with guideway structure
- The first steel beam is set at the Maintenance and Storage Facility
- Teams continue working on steel erection at the Maintenance and Storage Facility
- Crews work at the Maintenance and Storage Facility to pour slab on grade pours and construct underground utilities
- Following the erection of the vertical beams, horizontal beams will be set and the building will start to take shape
- Structural steel work continues at the Maintenance and Storage Facility while crews practice social distancing
- Bents at the future East Central Terminal Area station are prepared for concrete pours
- Station columns and bents are underway at the Intermodal Transportation Facility-West station
March 2020
- Formwork is placed around a column cage is inspected
- Guideway columns are under construction along the Automated People Mover alignment
- Falsework at future East Central Terminal Area is prepared for future placement of bents and upper columns
- Bents and guideway column cages at future ITF are placed
- Crews are hard at work in the future Maintenance and Storage Facility lot
- Formwork for the columns is prepared for future use
- LINXS places first slab on grade concrete at the future Maintenance and Storage Facility
- LINXS skilled craft prepares the Maintenance and Storage facility vapor barrier
- Concrete is finished following the first slab on grade pour at the Maintenance and Storage facility
February 2020
- The first cast-in-drilled-hole pile is drilled at the West Central Terminal Area station
- Rebar for the first cast-in-drilled-hole pile at the West Central Terminal Area station waits to be set in hole
- A cast-in-drilled-hole pile casing is oscillated into place at the future West Central Terminal Area station
- Rebar cages and casing for the cast-in-drilled-hole piles wait to be installed
- Rebar for the bent cap is in place at the future East Central Terminal Area station
- Crews advance foundation and utility construction at the Maintenance and Storage facility
- Guideway columns neighboring the future Intermodal Transportation Facility West Station are constructed
- Crews are busy at work constructing falsework at the future Automated People Mover stations
- Crews investigate utilities in the Central Terminal Area
January 2020
- First foundations for the guideway at the future Intermodal Transportation Facility East Station are drilled
- Crews are hard at work on the foundations for the Maintenance and Storage Facility
- LINXS supports the local skilled craft workforce on the Automated People Mover project
- The falsework steel is cut to specification using a track cutter
- LINXS crews install shoring boxes to prepare for utility relocations at the future West Central Terminal Area station
- LINXS employees observe confined space work being performed at the Intermodal Transportation Facility West Station
- The first columns are placed at the East Central Terminal Area station
- Falsework materials at the East Central Terminal Area are prepared to be set to allow for the future, elevated construction
- LINXS skilled craft prepares formwork to the column construction at Intermodal Transportation Facility-West
2019 Contruction Photos
Click here to view 2019 construction photos.
Renderings
- People Mover train above the terminal loop
- Central Terminal Area
- People Mover as it rides by iconic Theme Building
- Automated People Mover Guideway
- Intermodal Transportation Facility East
- People Mover train pulling into a station
- Intermodal Transportation Facility West
- Escalators leading to the Automated People Mover station
- Center CTA Station Interior